This page shows how City of Tucker · Right of Way Maintenance Services will be scored. It's built from tucker-ga-rfp-2026-008-row-maintenance.pdf, the actual RFP document, not a summary of it. The RFP says proposals are scored out of 100 points, and the items below add up to 100. Below that, you'll find 3 things that earn points, 12 rules that can get a proposal thrown out before scoring even starts, and 3 other things the RFP says about scoring that aren't tied to a specific scored item.
How to read this page
This page has three parts:How you'll be scored (the points table), What gets you thrown out (rules that can disqualify a proposal no matter how good it is), and Other things the RFP says about scoring (RFP sentences about scoring that aren't tied to a specific scored item). Use the tabs below to jump between them.
An orange box like is a button. Click it to see the exact words in the RFP, highlighted, so you can check our work against the real document.
not in source means the RFP is silent on that point. We never guess or fill it in for you.
The blank, striped boxes are for your team. We don't know who at your firm owns what, so those are left empty on purpose for someone to fill in.
Every quote on this page is copied from the RFP and linked to its page and line. The headings and labels are ours. We don't judge your bid, rank your chances, or suggest a strategy.
Bar sizes and percentages are simple math on the points the RFP prints.
How we checked this
We checked 30 lines in the RFP that talk about scoring or rejection. Every one of them is accounted for: 5 in How you'll be scored, 15 in What gets you thrown out, 4 in Other things the RFP says about scoring, and 7 read and set aside, each with its reason recorded in the matrix file.
Part 1
How you'll be scored
3 item(s), 100 points
View as:
From the RFP section: 4. Selection Criteria
35points35% of all the points
Item 1 of 3
Proposed Management Plan and Approach
What the RFP asks you to provide
Each proposer should include a summary of their proposed management plan. The management plan should describe the number of crews and seasonal personnel, if any, proposed to accomplish the required work.
What the scorer will look for
The proposal shall outline the plan that the company will use to provide the most effective delivery of the requested services as outlined in the Scope of Work.
Where it goes in your proposal
not in sourceThe RFP doesn't say
Status
Where your team will get it
Lead for this section
Reviewer for this section
35points35% of all the points
Item 2 of 3
Qualifications and Similar Project Experience of the Company and Staff
What the RFP asks you to provide
Provide information on supervisory personnel to be assigned to this contract, including for the project superintendent, road maintenance foreman, and stormwater foreman The proposal should identify any applicable certifications held by key personnel who will perform the work. Provide copies of appropriate required licenses.
What the scorer will look for
The proposal must give a detailed report of related experiences that demonstrate the ability of the proposer to perform requested services as outlined in the Scope of Work. The proposal shall include sufficient information to indicate the abilities, qualifications, and experience of all persons who would be assigned to provide the required services.
Where it goes in your proposal
not in sourceThe RFP doesn't say
Status
Where your team will get it
Lead for this section
Reviewer for this section
30points30% of all the points
Item 3 of 3
Cost Proposal
What the RFP asks you to provide
Proposers shall provide lump sum costs for basic services per the Cost Proposal Form provided. Proposers shall also submit the Unit Cost Schedule per the form provided.
What the scorer will look for
In scoring against stated criteria, the City may consider such factors as accepted industry standards and a comparative evaluation of all other qualified RFP responses in terms of differing price, quality, and contractual factors.
Where it goes in your proposal
Cost Proposal (form provided)
Status
Where your team will get it
Lead for this section
Reviewer for this section
Status
What the RFP will score (their exact words)
Points for this item
What the RFP asks you to provide
Where your team will get it
What the scorer will look for
Where it goes in your proposal
Lead for this section
Reviewer for this section
From the RFP section: 4. Selection Criteria
1Proposed Management Plan and Approach
35
Each proposer should include a summary of their proposed management plan. The management plan should describe the number of crews and seasonal personnel, if any, proposed to accomplish the required work.
The proposal shall outline the plan that the company will use to provide the most effective delivery of the requested services as outlined in the Scope of Work.
not in sourceThe RFP doesn't say
2Qualifications and Similar Project Experience of the Company and Staff
35
Provide information on supervisory personnel to be assigned to this contract, including for the project superintendent, road maintenance foreman, and stormwater foreman The proposal should identify any applicable certifications held by key personnel who will perform the work. Provide copies of appropriate required licenses.
The proposal must give a detailed report of related experiences that demonstrate the ability of the proposer to perform requested services as outlined in the Scope of Work. The proposal shall include sufficient information to indicate the abilities, qualifications, and experience of all persons who would be assigned to provide the required services.
not in sourceThe RFP doesn't say
3Cost Proposal
30
Proposers shall provide lump sum costs for basic services per the Cost Proposal Form provided. Proposers shall also submit the Unit Cost Schedule per the form provided.
In scoring against stated criteria, the City may consider such factors as accepted industry standards and a comparative evaluation of all other qualified RFP responses in terms of differing price, quality, and contractual factors.
Cost Proposal (form provided)
Total points
100
Part 2
What gets you thrown out (12)
Rules in the RFP that can remove a proposal before scoring. Grouped by kind of rule, in the order each kind first appears; the Table view lists them in RFP order.
Turned in late3
Late bids will not be considered.
Bids received after the bid deadline will be filed unopened.
Late submittals will not be accepted.
The agency keeps the right to reject proposals2
The City of Tucker reserves the right to reject any and all bids or any part, to waive any formalities to make an award and to re-advertise in the best interest of the City.
reject any or all Proposals received in response to this RFP;
Doesn't meet the agency's requirements4
All Proposals will initially be classified as either “responsive” or “non‐responsive”. Proposals may be found non‐responsive any time during the evaluation process or contract negotiation if any of the required information is not provided; the submitted price is found to be excessive or inadequate as measured by criteria stated in the RFP; or the Proposals is not within the plans and specifications described and required in the RFP. If a Proposal is found to be non‐responsive, it will not be considered further.
The procurement officer will determine whether an offeror has met the standards of responsibility. Such a determination may be made at any time during the evaluation process and through contract negotiation if information surfaces that would result in a determination of non‐responsibility. If an offeror is found non‐responsible, the determination must be in writing, made a part of the procurement file, and mailed to the affected offeror.
Failure to meet these requirements will result in the Proposals being determined
and the entire submittal will be rejected.
Missing something required1
Incomplete submittals will not be considered.
Broke a formatting or delivery rule (like a page limit)1
Any other supplemental information and pages outside the page limit will not be reviewed and will be considered as non‐responsive to the page limit requirement.
The RFP says this specifically disqualifies a proposal1
Information or materials presented by offerors outside the formal response or subsequent discussion/negotiation or “best and final offer,” if requested, will not be considered, will have no bearing on any award, and may result in the offeror being disqualified from further consideration.
Late bids will not be considered.Turned in late
Bids received after the bid deadline will be filed unopened.Turned in late
The City of Tucker reserves the right to reject any and all bids or any part, to waive any formalities to make an award and to re-advertise in the best interest of the City.The agency keeps the right to reject proposals
All Proposals will initially be classified as either “responsive” or “non‐responsive”. Proposals may be found non‐responsive any time during the evaluation process or contract negotiation if any of the required information is not provided; the submitted price is found to be excessive or inadequate as measured by criteria stated in the RFP; or the Proposals is not within the plans and specifications described and required in the RFP. If a Proposal is found to be non‐responsive, it will not be considered further.Doesn't meet the agency's requirements
The procurement officer will determine whether an offeror has met the standards of responsibility. Such a determination may be made at any time during the evaluation process and through contract negotiation if information surfaces that would result in a determination of non‐responsibility. If an offeror is found non‐responsible, the determination must be in writing, made a part of the procurement file, and mailed to the affected offeror.Doesn't meet the agency's requirements
reject any or all Proposals received in response to this RFP;The agency keeps the right to reject proposals
Incomplete submittals will not be considered.Missing something required
Late submittals will not be accepted.Turned in late
Failure to meet these requirements will result in the Proposals being determinedDoesn't meet the agency's requirements
and the entire submittal will be rejected.Doesn't meet the agency's requirements
Any other supplemental information and pages outside the page limit will not be reviewed and will be considered as non‐responsive to the page limit requirement.Broke a formatting or delivery rule (like a page limit)
Information or materials presented by offerors outside the formal response or subsequent discussion/negotiation or “best and final offer,” if requested, will not be considered, will have no bearing on any award, and may result in the offeror being disqualified from further consideration.The RFP says this specifically disqualifies a proposal
Part 3
Other things the RFP says about scoring (3)
Lines about scoring that aren't tied to a specific scored item. Grouped by reason, in the order each reason first appears; the Table view lists them in RFP order.
Mentioned inside a scored item above, but doesn't carry its own points1
Age and condition of equipment will be factored into contractor scoring for these services.
Explains how scoring works overall, not a separate scored item1
Proposals will be evaluated and scored in categories. Each category is assigned a maximum point value.
Happens later in the process; its scoring is not in this RFP document1
The City reserves the right to invite Offerors to present their proposal to the Evaluation Team. Evaluation criteria for such presentations will be provided to offerors prior to presentations.
Age and condition of equipment will be factored into contractor scoring for these services. Mentioned inside a scored item above, but doesn't carry its own points
Proposals will be evaluated and scored in categories. Each category is assigned a maximum point value. Explains how scoring works overall, not a separate scored item
The City reserves the right to invite Offerors to present their proposal to the Evaluation Team. Evaluation criteria for such presentations will be provided to offerors prior to presentations. Happens later in the process; its scoring is not in this RFP document
Boxes your team still needs to fill in: 12 of them. Numbered text the checklist was checked against: ../fixtures/tucker-ga-rfp-2026-008-row-maintenance.source.txt